Skip to main content

GRID Power Act (S. 465)

Introduced
Introduced 2/6/2025•119th Congress•Senate

Latest Action

Placed on Senate Legislative Calendar under General Orders. Calendar No. 698.

11/12/2026 • Senate

Summary

Guaranteeing Reliability through the Interconnection of Dispatchable Power Act or the GRID Power Act

This bill requires the Federal Energy Regulatory Commission (FERC) to issue and periodically review a rule that revises the approval process for interconnection requests of generating units that produce electricity to prioritize dispatchable power projects (e.g., certain fossil fuel projects). 

Under the bill, dispatchable power generally refers to an electric energy generation resource, such as a generating unit that produces electricity from fossil fuels, capable of providing known and forecastable electric supply in time intervals necessary to ensure grid reliability. Currently, FERC receives interconnection requests from those projects and other generating units, such as units that produce electricity from renewable energy. Interconnection requests are requests from generating units to connect to the high voltage transmission lines of the electric grid.

First, the rule must address the efficiency and effectiveness of the existing procedures for processing interconnection requests to ensure that new dispatchable power projects that improve grid reliability and resource adequacy can interconnect to the electric grid quickly, cost-effectively, and reliably. 

Second, the rule must revise the pro forma Large Generator Interconnection Procedures, and the pro forma Large Generator Interconnection Agreement as appropriate, to authorize transmission providers to submit proposals to FERC to prioritize new dispatchable power projects that will improve grid reliability and resource adequacy by assigning those projects higher positions in the interconnection queue of the provider. FERC must review and approve or deny such proposals within 60 days after the proposal is submitted.

Introduced in Senate • 2/6/2025

Enter your district to see how this bill affects your community
-

Topics & Subjects

Policy Area: Energy
Electric power generation and transmissionEnergy efficiency and conservationEnergy storage, supplies, demand

Congressional Votes (0)

No recorded votes yet

Roll call votes will appear here as the bill moves through Congress

Related Federal Spending

Sponsor & Cosponsors (5)

Party Breakdown

0
Democrats
5
Republicans
0
Independents

Sponsor

S[
Sen. Hoeven, John [R-ND]

Republican • ND

Sponsored 2/6/2025

Cosponsors (4)

S[
Sen. Young, Todd [R-IN]

R-IN

Joined 2/6/2025

S[
Sen. Marshall, Roger [R-KS]

R-KS

Joined 2/26/2025

S[
Sen. Moreno, Bernie [R-OH]

R-OH

Joined 4/28/2025

S[
Sen. McCormick, David [R-PA]

R-PA

Joined 9/15/2026

Bill Journey

Originated in the Senate

Introduced

February 6, 2025

Committee Review

April 15, 2026

Committee on Energy and Natural Resources Subcommittee on Energy. Hearings held. With printed Hearing: S.Hrg. 119-366.

Floor Debate

Passed Chamber

Other Chamber

President

Enacted into Law

Text Versions (2)

Reported to Senate11/12/2026
Introduced in Senate2/6/2025

Details

Bill TypeS
Current StatusIntroduced
Cosponsors4

Sources and method

· Record updated Nov 17, 2026
  • Congress.govLibrary of Congress
    Status, actions, sponsors, cosponsors, committees and text
    Record updated Nov 17, 2026 · Loaded Nov 17, 2026, 8:10 AM ET
  • CRS bill summaryCongressional Research Service, via Congress.gov
    Official summary
    Summary of the “Introduced in Senate” version, Feb 6, 2025 · Loaded Nov 17, 2026, 8:10 AM ET
  • USAspending.govU.S. Department of the Treasury
    Related Federal Spending section
  • FEC filingsFederal Election Commission
    Funding & Lobbying section
  • Lobbying disclosures (LDA)Secretary of the Senate and Clerk of the House
    Funding & Lobbying section

All sources: Public domain (17 U.S.C. § 105) · Method: Data sources → · Campaign finance →

AI-written text on this page is labeled where it appears. It is written from the sources above and is not a source itself. How we analyze data →

Dates shown where the source reports one. “Loaded” is when CIV.IQ last fetched the record.