Latest Action
Received in the Senate and Read twice and referred to the Committee on Energy and Natural Resources.
9/19/2025 • Senate
Summary
Guaranteeing Reliability through the Interconnection of Dispatchable Power Act or the GRID Power Act
This bill requires the Federal Energy Regulatory Commission (FERC) to issue and periodically review a rule that revises the approval process for interconnection requests of generating units that produce electricity to prioritize dispatchable power projects (e.g., certain fossil fuel projects).
Under the bill, dispatchable power generally refers to an electric energy generation resource, such as a generating unit that produces electricity from fossil fuels, capable of providing known and forecastable electric supply in time intervals necessary to ensure grid reliability. Currently, FERC receives interconnection requests from those projects and other generating units, such as units that produce electricity from renewable energy. Interconnection requests are requests from generating units to connect to the high voltage transmission lines of the electric grid.
First, the rule must address the efficiency and effectiveness of the existing procedures for processing interconnection requests to ensure that new dispatchable power projects that improve grid reliability and resource adequacy can interconnect to the electric grid quickly, cost-effectively, and reliably.
Second, the rule must revise the pro forma Large Generator Interconnection Procedures, and the pro forma Large Generator Interconnection Agreement as appropriate, to authorize transmission providers to submit proposals to FERC to prioritize new dispatchable power projects that will improve grid reliability and resource adequacy by assigning those projects higher positions in the interconnection queue of the provider. FERC must review and approve or deny such proposals within 60 days after the proposal is submitted.
Introduced in House • 2/6/2025
Topics & Subjects
CBO Cost Estimates (1)
Amendments (1)
This bill has 1 amendment proposed or adopted.
View all amendments on Congress.govRelated Federal Spending
Sponsor & Cosponsors (18)
Party Breakdown
Sponsor
Cosponsors (17)
Bill Journey
Originated in the House
Introduced
February 6, 2025
Committee Review
June 5, 2025
Forwarded by Subcommittee to Full Committee by the Yeas and Nays: 16 - 14.
Floor Debate
September 18, 2025
Passed Chamber
Other Chamber
President
Enacted into Law
Text Versions (4)
Committee Reports (1)
Related Bills (2)
H.Res. 707
Providing for consideration of the bill (H.R. 4922) to limit youth offender status in the District of Columbia to individuals 18 years of age or younger, to direct the Attorney General of the District of Columbia to establish and operate a publicly accessible website containing updated statistics on juvenile crime in the District of Columbia, to amend the District of Columbia Home Rule Act to prohibit the Council of the District of Columbia from enacting changes to existing criminal liability sentences, and for other purposes; providing for consideration of the bill (H.R. 5143) to establish standards for law enforcement officers in the District of Columbia to engage in vehicular pursuits of suspects, and for other purposes; providing for consideration of the bill (H.R. 5140) to lower the age at which a minor may be tried as an adult for certain criminal offenses in the District of Columbia to 14 years of age; providing for consideration of the bill (H.R. 5125) to amend the District of Columbia Home Rule Act to terminate the District of Columbia Judicial Nomination Commission, and for other purposes; providing for consideration of the bill (H.R. 1047) to require the Federal Energy Regulatory Commission to reform the interconnection queue process for the prioritization and approval of certain projects, and for other purposes; providing for consideration of the bill (H.R. 3015) to reestablish the National Coal Council in the Department of Energy to provide advice and recommendations to the Secretary of Energy on matters related to coal and the coal industry, and for other purposes; providing for consideration of the bill (H.R. 3062) to establish a more uniform, transparent, and modern process to authorize the construction, connection, operation, and maintenance of international border-crossing facilities for the import and export of oil and natural gas and the transmission of electricity; and for other purposes.
S. 465
GRID Power Act