H.R. 3144
Referred to CommitteeTo provide for operations of the Federal Columbia River Power System pursuant to a certain operation plan for a specified period of time, and for other purposes.
Latest Action
Received in the Senate and Read twice and referred to the Committee on Environment and Public Works.
4/26/2018 • Senate
Summary
(Sec. 2) This bill requires the Bureau of Reclamation, the Bonneville Power Administration, and the U.S. Army Corps of Engineers to operate the Federal Columbia River Power System (FCRPS) in a manner consistent with the document titled "Endangered Species Act Section 7(a)(2) Supplemental Biological Opinion," dated January 17, 2014, until the later of September 30, 2022, or the date upon which a subsequent final biological opinion for FCRPS operations is in effect with no pending further judicial review.
(Sec. 3) Such entities may amend the supplemental opinion and operate the FCRPS accordingly before such date if the entities agree that: (1) the amendments are necessary for public safety or transmission and grid reliability; or (2) the actions, operations, or other requirements that the amendments remove are no longer warranted.
(Sec. 4) No structural modification, action, study, or engineering plan may restrict electrical generation at any FCRPS hydroelectric dam or limit navigation on the Snake River in Washington, Oregon, or Idaho unless authorized by Congress.
Passed House amended • 4/25/2018
Topics & Subjects
Amendments (1)
This bill has 1 amendment proposed or adopted.
View all amendments on Congress.govCongressional Votes (2)
On Passage
April 25, 2018
On Motion to Recommit with Instructions
April 25, 2018
Related Federal Spending
Sponsor & Cosponsors (9)
Party Breakdown
Sponsor
Cosponsors (8)
Bill Journey
Originated in the House
Introduced
June 29, 2017
Committee Review
October 12, 2017
Floor Debate
April 25, 2018
Passed Chamber
April 25, 2018
Other Chamber
President
Failed
April 25, 2018