S. 1526
IntroducedConstruction Consensus Procurement Improvement Act of 2015
Latest Action
Placed on Senate Legislative Calendar under General Orders. Calendar No. 656.
10/27/2016 • Senate
Summary
Construction Consensus Procurement Improvement Act of 2015
(Sec. 3) This bill modifies the design-build selection procedures used by federal agencies soliciting offers to enter into civilian contracts for the design and construction of a public building, facility, or work. Two-phase selection procedures (i.e., submission of qualifications and then the submission of price and technical proposals in response to a request for proposal) must be used when a contracting officer determines that a project has a value of $750,000 or greater. But for contracts valued at less than $750,000, the contracting officer makes the same determination under current law as to whether the use of two-phase selection procedures is appropriate when the officer anticipates at least three offers for the contract.
Federal agencies must report, each year through FY2021, on each instance where the agency awarded a design-build contract in which: (1) more than five finalists were selected for phase-two requests for proposals, or (2) the contract or order was awarded without using two-phase selection procedures. The Government Accountability Office must report on agency compliance with design-build contract procedures.
(Sec. 4) The Federal Acquisition Regulatory Council must amend the Federal Acquisition Regulation to prohibit the use of reverse auctions as part of the two-phase selection procedure for awarding contracts for construction and design services. A "reverse auction," with respect to procurement by an agency, is: (1) a real-time auction conducted through an electronic medium among at least two offerors who compete by submitting bids for a supply or service contract with the ability to submit revised lower bids before the closing of the auction; and (2) the award of the contract, delivery order, task order, or purchase order to the offeror based on the price obtained through the auction process.
Reported to Senate with amendment(s) • 10/27/2016
Topics & Subjects
Congressional Votes (0)
No recorded votes yet
Roll call votes will appear here as the bill moves through Congress
Related Federal Spending
Sponsor & Cosponsors (4)
Party Breakdown
Sponsor
Cosponsors (3)
Bill Journey
Originated in the Senate
Introduced
June 8, 2015
Committee Review
February 10, 2016
Committee on Homeland Security and Governmental Affairs. Ordered to be reported with an amendment in the nature of a substitute favorably.
Floor Debate
Passed Chamber
Other Chamber
President
Enacted into Law