H.R. 3447
IntroducedTo extend the deadline for commencement of construction of a hydroelectric project.
Latest Action
Received in the Senate. Read twice. Placed on Senate Legislative Calendar under General Orders. Calendar No. 396.
3/16/2016 • Senate
Summary
(Sec. 1) This bill authorizes the Federal Energy Regulatory Commission (FERC) to extend by six years the time period during which Wilkesboro Hydroelectric Company is required to commence construction on the W. Kerr Scott Hydropower Project located on the Yadkin River in Wilkes County, North Carolina.
In addition, FERC must reinstate the construction license if it is expired.
Passed House amended • 3/15/2016
Topics & Subjects
Related Federal Spending
Sponsor & Cosponsors (1)
Sponsor
No cosponsors yet
Cosponsors may be added as the bill moves through Congress
Bill Journey
Originated in the House
Introduced
September 8, 2015
Committee Review
February 10, 2016
Subcommittee Consideration and Mark-up Session Held.
Floor Debate
March 14, 2016
Passed Chamber
March 15, 2016
Other Chamber
President
Enacted into Law
Text Versions (3)
Related Bills (7)
S. 2083
A bill to extend the deadline for commencement of construction of a hydroelectric project.
H.R. 4416
To extend the deadline for commencement of construction of a hydroelectric project.
S. 2012
Energy Policy Modernization Act of 2016
H.R. 4434
To extend the deadline for commencement of construction of a hydroelectric project.
H.R. 951
To extend the deadline for commencement of construction of a hydroelectric project.
H.R. 4411
To extend the deadline for commencement of construction of a hydroelectric project.
H.R. 4412
To extend the deadline for commencement of construction of a hydroelectric project.